We
are pleased to announce that on September 21, 2015 the Kitsap County Hearing
examiner approved our request to haul aggregate via Werner Road instead of
Northlake Way. The ruling also provides us with the ability to move the
processing facility to another location along the South access route. These
were the two major issues raised by the public during the original CUP process.
We see this as a long term win/win for the community and Ueland Tree Farm.
We see this as a long term win/win for the community and Ueland Tree Farm.
This link will take you to the Hearing Examiners
decision